Page 1 of 1

15 back to 14?

PostPosted: Tue Jul 03, 2018 6:01 am
by DarekSepiolo
Hi,
I did a project in 14.3 last year and upgraded the database to 15 later on this year. My client is still using 14.3 and there's now way he can upgrade to 15.
What is the easiest way to deliver the graded project to him?
Thank you

Re: 15 back to 14?

PostPosted: Tue Jul 03, 2018 8:13 am
by Sam Steti
Export the project (.drp) which he imports and also give him original footage of course...

Re: 15 back to 14?

PostPosted: Tue Jul 03, 2018 11:06 am
by Peter Chamberlain
V15 projects are not designed to run in v14.
I would be surprised if that works all correctly.

Re: 15 back to 14?

PostPosted: Tue Jul 03, 2018 11:45 am
by Uli Plank
The only way I can think of is a Premiere or FCP 7 export, he should be able to import that.
BUT: all current effects and grading will be baked in. Might still be OK for minor corrections or re-editing and could possibly save your behind.

But don't say you haven't been warned, both when you installed 15 and when you opened the old database!

Re: 15 back to 14?

PostPosted: Wed Jul 04, 2018 9:32 am
by DarekSepiolo
Thank you for all your help :)